Description
This is an installation report detailing placement of the integrated fiber-optic cable behind casing in Utah FORGE well 16B(78)-32. These activities occurred in July of 2023 immediately after the drilling of 16B. This report was prepared by the FOGMORE R&D project (Fiber Optic MOnitoring for Reservoir Evolution), Utah FORGE R&D Project 3-2417. For clarity, several cables were installed behind casing in well 16B. This report only documents the cable installed by the FOGMORE Utah FORGE project. A second cable was installed by a team led by UT Austin and Shell.
Resources
| Name | Format | Description | Link |
|---|---|---|---|
| Fiber Installation Report.pdf | This report details all steps involved in the installation process. Information includes design specifications, preparation, installation execution, and post installation checks. | Open resource |