Hazard studies Hydraulic development from Viterne to Maizières Addendum 3
Description
This contract has several phases.
The second phase, involving the study of hazards and the financial dimension of future work, began in order of priority.
service in April 2023, for a period of 8 months and then extended until 3 May 2024 and then until 5 July
2024.
The results of Phase 2 were presented at the Steering Committee meeting on 28 June and this requires:
a few times by the design office in order to finalise the deliverables.
In addition, the EPTB is awaiting a clear response from the State services regarding the stage
regulation provided for in the optional tranche of this contract. This is why the
The optional tranche has not yet been consolidated.
For all these reasons, Phase 2 (and the market) should be extended until Friday 4 October 2024.
Addendum notified by EPTB to the holder on 2 July 2024 (2024-07-02).