Hazard study Hydraulic development of the Viterne à Maizières Addendum 1

Description

This contract has several phases.
The timing of the transmission of geotechnical data to the holder resulted in a schedule delay. It is therefore necessary to extend this contract until 3 May 2024.
New duration of the contract:
Addendum notified by EPTB to the holder on 16 October 2023 (2023-10-16).